Is This Job Still Making Money? Three Numbers That Mislead You Mid-Job

Is This Job Still Making Money? Three Numbers That Mislead You Mid-Job

Halfway through a job, there is one question that matters more than the rest: is this job still making the money we bid it to make?

Most shops answer it by looking at a job report. The trouble is that three of the most common numbers on that report can tell you everything is fine while the margin is already slipping. None of them is wrong, exactly. They are just answering a different question than the one you asked.

To show how, we built a demo HVAC company in crew&cost with made-up jobs and customers, and ran one of its jobs into a problem on purpose. Everything below comes from that demo. The pattern is real; the company is not.

The Job

A three-unit rooftop changeout for a medical office in Carrollton. The numbers at signing:

  • Contract: $64,000

  • Budget: $53,400 (labor $15,600, materials $31,500, crane $3,600, electrical sub $2,700)

  • Planned profit: $10,600, about 16.6%

Two weeks in, the crew found the existing curbs out of square. Fixing them took a couple of extra crew days and some additional curb steel. Nobody did anything wrong. It is the kind of surprise every rooftop job carries.

At that point, labor stood at $16,800 against a $15,600 budget, and startup, controls, and the electrical work were still ahead.

Now look at what a typical report says about it.

Number 1: Percent Complete That Measures Spending, Not Progress

A lot of job reports calculate percent complete from cost: dollars spent divided by dollars budgeted. On this job, that is $52,200 of $53,400, so the report says the job is 97.8% complete.

It is not. The units were bought on day one, so most of the material budget was spent before a wrench turned. The crane was a single day. Startup, controls, balancing, and the electrical sub are all still ahead.

Cost-based percent complete measures how fast you are spending, not how much work is done. On jobs with expensive equipment bought up front, which describes most HVAC and mechanical changeouts, it will always run ahead of reality. Worse, a job that is overrunning looks further along, because overruns are spending.

It also quietly breaks every "to date" number built on top of it. If revenue earned is credited by the share of budget spent, then margin to date works out to your bid margin on every job, every week, until the budget runs out. On this job the report showed a healthy 16.6% to date, the same as the bid, while the job was already sliding. That number cannot warn you. The math will not let it.

The fix: measure progress against what the job will actually cost, not what you budgeted. That takes one more input, covered in the next section: what is left to spend.

Number 2: Projected Profit That Never Moves

Many reports show a projected profit for the job. Check how it is calculated. Often it is simply contract minus budget, which on this job is $10,600. That number was $10,600 on the day the job was signed, and it will still say $10,600 the day the job closes, no matter what happens in between.

That is not a projection. It is the bid, restated.

A real projection has to use what you have actually spent. A simple, conservative way to do it:

  1. For each cost category, take whichever is larger: the budget, or what you have spent so far.

  2. Add those up. That is your forecast cost at completion.

  3. Contract minus forecast cost is your projected profit.

On this job:

Category

Budget

Spent so far

Use

Labor

$15,600

$16,800

$16,800

Materials

$31,500

$31,800

$31,800

Crane

$3,600

$3,600

$3,600

Electrical sub

$2,700

$0

$2,700

Forecast cost

$54,900

Projected profit: $64,000 − $54,900 = $9,100, or 14.2%, down $1,500 from plan.

Better than a number that never moves. But notice what it assumes: labor is already over budget, so the method treats labor as finished. Startup and controls are still ahead. This is the best case, not the expected case.

The Missing Input: What Is Left to Spend

Construction cost people call it estimate to complete. Once a week, someone who knows the job answers one question per category: how much more will this take to finish?

On this job the foreman says startup, controls, and balancing will take about 65 more crew hours, roughly $3,120 at the loaded rate. The electrical sub has not billed yet: $2,700. Materials and the crane are done.

Category

Spent so far

Left to spend

Forecast

Labor

$16,800

$3,120

$19,920

Materials

$31,800

$0

$31,800

Crane

$3,600

$0

$3,600

Electrical sub

$0

$2,700

$2,700

Forecast cost

$52,200

$5,820

$58,020

Projected profit: $64,000 − $58,020 = $5,980, or 9.3%, down $4,620 from the $10,600 that was planned. That is not a rounding error. It is nearly half the profit on the job.

It also fixes Number 1. Progress measured against the forecast is $52,200 of $58,020, or 90% complete, not 98%. Margin to date drops to 9.3%, the same as the projection, because both now measure the same job. The numbers finally agree with each other.

crew&cost job summary for a demo rooftop unit changeout: $64,000 contract, $52,200 actual cost, $10,600 planned profit, $5,980 projected profit at 9.3% shown in red, down $4,620 from plan, with earned revenue, gross profit and margin to date of 9.3%.

Number 3: Totals That Let One Category Hide Another

The third trap is comparing totals instead of categories. Suppose the materials on this job had come in $1,200 under budget instead of $300 over. Total spending would look almost exactly on plan, and the labor overrun would disappear inside the job total.

But materials savings do not pay for labor overruns on the next job. If you price your next rooftop changeout the same way, the labor problem comes with you, and you may not get lucky on materials twice.

That is why the forecast works category by category. An overrun in one category is never cancelled out by an underrun in another. Each line has to stand on its own.

Why This Matters on the Next Bid

Catching the slip mid-job protects this job. The bigger payoff is the next bid.

The same demo company finished a split-system and duct replacement for a dental office in an older building. Labor ran $3,300 over because the ductwork above the ceiling did not match the drawings. That job closed at a 6.3% margin against a planned 18.9%.

When the estimator builds the next changeout bid, that job should show up as a warning, not get buried under the jobs that went well. In crew&cost, comparable past jobs are ranked by how closely they match the new bid, and a low-margin match is always kept in the list when one exists, so the estimator sees what went wrong last time before pricing labor the same way again.

crew&cost Smart Bid panel for a new rooftop unit bid, listing comparable past jobs by match, including a dental office job in red at 6.3% margin.

A Ten-Minute Weekly Check You Can Run on Paper

You do not need software to start doing this. For each active job, once a week:

  1. Write down the planned profit from the bid: contract minus budget.

  2. List each cost category with what you have spent so far.

  3. Ask the foreman what is left, by category, in hours or dollars. Convert hours at your loaded rate. Do not skip a category because it is already over budget; those are the ones that surprise you.

  4. Add spent plus left to spend for each category. That is your forecast cost. Subtract it from the contract.

  5. Compare to planned profit. If it has dropped, you now know which category did it, and you still have time to do something about it: a conversation with the customer about a change, a crew adjustment, or a note for the next bid.

Ten minutes per job. The point is not precision. The point is that the number moves when the job moves.

Where crew&cost Fits

1Site2See builds crew&cost for trade contractors. Costs logged during the week, plus a weekly "left to spend" update per category, give you the forecast, progress, and projected profit above without a spreadsheet. The job page shows how far an active job has dropped below its plan, flags an estimate that has not been updated in a week, and carries what happened into the next bid.

But the habit comes first. If costs are not logged while the work happens, no tool can forecast anything. If you would like help figuring out where your own job numbers are coming from, and whether they are telling you the truth, that is the kind of walkthrough we do.

The Question to Ask This Week

Pick one job that is running right now and ask: if this job finished today at the rate it is going, what would it actually make?

If the only number you can find is the one from the bid, that is your answer, and your starting point.